GHS201,000 SOCO irrigation projects fail to provide water for Bolgatanga farmers

By Moses Apiah Date: August 4, 2026
4th estate feature images 1
SHARE

Two irrigation projects built at a cost of more than GHS201,000 in Bolgatanga in the Upper East Region have failed to provide enough water for farmers to cultivate crops during the dry season.

The mechanised boreholes were constructed in 2024 in the Amogrebisi and Daweo communities under the World Bank-funded Gulf of Guinea Northern Regions Social Cohesion Project, known as SOCO.

They were intended to provide a reliable supply of water for vegetable farming and help residents earn income throughout the year.

- Advertisement -

But farmers say the systems produce too little water and cannot reach the areas where they cultivate their crops.

Danwoe project
Dawoe water project

“The project is not giving us the water we need for dry-season farming,” said Atubiga Ernest, a 45-year-old farmer in Amogrebisi.

Another farmer, Abisibo Akolgo, said: “The water from this project cannot even reach where we farm.”

The two projects cost a combined GHS201,599.50.

- Advertisement -
Sumbrungu project on Ernests farmland
Amogrebisi water project

Farmers say they were not consulted

Farmers in both communities told The Fourth Estate that they were not properly involved in the planning and design of the projects.

Afedo Asoria, a vegetable farmer in Amogrebisi, said the facility could have helped families increase their incomes and pay their children’s school fees if it had worked as promised.

Afedo Asoria Sumbrungu
Afedo Asoria, a vegetable farmer in Amogrebisi

“Nobody consulted us,” he said. “They only informed us that they were bringing a SOCO irrigation project. Had they involved us during planning, we would have suggested ideas that would make it work.”

In Daweo, farmer Akolgo George said the project had failed to serve its intended purpose.

“They might as well remove it instead of saying they provided irrigation for us when we cannot use it,” he said.

- Advertisement -

James Alagemah, a farmer and plumber, said residents raised concerns as soon as construction began.

He said the three-quarter-inch outlet pipe installed by the contractor was too small to provide enough water for irrigation.

James Alagemah Danwoe farmer
James Alagemah, a farmer and plumber

“The moment the contractor started work, we realised the project would fail,” he said.

According to Mr Alagemah, it took between eight and nine hours to fill the tank during the commissioning of the project.

“Imagine 30 to 40 farmers depending on that. How can this support commercial farming?” he asked.

Documents show different tank sizes

An investigation by The Fourth Estate revealed inconsistencies between official documents and what was constructed in the two communities.

Contract documents sighted by The Fourth Estate indicated that each system was to include a 1.5-horsepower pump, irrigation pipelines and an elevated 10,000-litre water tank.

However, records obtained from the Ministry of Local Government, Decentralisation and Rural Development referred to 3,500-litre tanks.

At the project sites, The Fourth Estate found tanks with a capacity of only 350 litres.

350 litre water tank 1
Overhead tank at one of the project sites

The facilities were also fitted with three-quarter-inch outlet pipes, which experts say were more suitable for domestic water supply than commercial irrigation.

Experts question the design

Hydrologist Richard Abaare said the size of the pipes suggested that the systems were designed mainly for household use.

“The use of a three-quarter-inch outlet pipe suggests the pumps are likely to be one horsepower or even 0.75 horsepower, which is generally designed for domestic use,” he said.

Drilling expert Nyaaba Adongo said commercial irrigation normally required pumps of between 2 and 2.5 horsepower to supply enough water.

The concerns were also raised by former Bolgatanga Municipal Chief Executive, Rex Asanga, who was in office when the projects were implemented.

Rex Asanga
Rex Asanga, former Municipal Chief Executive of Bolgatanga

Mr Asanga said the Assembly had originally planned the facilities as irrigation systems after farmers identified water shortages as a major obstacle to dry-season farming.

“The whole concept was to tap underground water to support dry-season irrigation,” he said.

But he said inspections before completion showed that the systems were different from what had been planned.

“When I inspected the projects before completion, I realised the tanks were far too small,” he said.

Mr Asanga said he wrote to the Municipal Planning Officer and Municipal Engineer asking them to explain why the facilities appeared to have been designed for domestic use rather than irrigation.

One of the letters, seen by The Fourth Estate, stated that the completed facilities appeared to be potable water systems.

Mr Asanga regretted that the controversy had damaged the Assembly’s credibility because residents now say they had been given projects that could not meet their needs.

Assembly officials reject criticism

The former Municipal Engineer, Daniel Atchulo, rejected Mr Asanga’s criticism and questioned whether the former Chief Executive had the technical expertise to assess the designs.

Mr Atchulo maintained that the contractor completed the projects according to the approved specifications. He also said he had not received the query letter Mr Asanga said he issued.

The Municipal Planning Officer, Juliana Agyeyomah, declined to respond directly to the concerns raised in the letter.

“I have my personal reservations about this letter,” she said. “If people want to open Pandora’s box, it will not be me.”

She said officials should focus on finding solutions rather than assigning blame.

The current Municipal Engineer, Owusu Emmanuel Kwaku, confirmed that Assembly contract documents provided for 10,000-litre elevated tanks and 1.5-horsepower pumps.

The documents showed that the mechanisation component of each project, including the tank, pump, electrical connections and irrigation pipes, was budgeted at GHS40,000.

The remaining funds covered other construction costs, bringing the total expenditure on the two projects to GHS201,599.50.

Contractor says he followed instructions

The contractor, Osman Murtala of Al-Kahf Company Limited, denied responsibility for the shortcomings.

He said he carried out the work according to the specifications and directions given by Assembly engineers.

“I delivered exactly what was in the contract documents,” he said.

“I worked under the Assembly engineers. Whatever they instructed me to do was what I did.”

The conflicting accounts leave unanswered questions about who approved the final designs and why the facilities built in Amogrebisi and Daweo differed from specifications contained in some official documents.

For farmers in the two communities, however, the immediate concern is that the projects have failed to provide the water they were promised.

The result has been lost farming opportunities, reduced incomes and public money spent on facilities that offer little practical benefit, they say.

TAGGED:BOLGATANGAcp_spotlightIRRIGATION PROJECTSSOCO
Share This Article
Facebook Whatsapp Whatsapp LinkedIn Telegram Email
Leave a comment Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

- Advertisement -

LATEST STORIES

ministers featured image
Terrible NLA-KGL Deal: Government indulges in merry-go-round over release of interministerial committee report
cover image vv2
$33 million loans, grants spent on streetlights in 14 years, yet darkness prevails
PHOTO 2025 11 13 09 34 43 scaled 1
Government’s attempt to revive poultry industry struggles to deliver on key promises
4th estate feature images
Quarry blasts leave a trail of damage in Pwalugu
NDC illegal 1
NDC boys rack up GHS 5million electricity debt at illegal mine despite anti-galamsey crackdown

You Might Also Like

Uncover the stories that related to the post
The Fouerg Estate journalists win award
General News

The Fourth Estate Journalists honoured for galamsey exposé

5F0A0279
General News

Delays, distrust, and deaths: Inside Ghana’s election collation crisis

Dag
General News

Court slaps fresh GH¢6,000 cost against Lighthouse to amend defence

Screen Shot 2021 04 21 at 3.45.15 PM
Anti-CorruptionGeneral News

FDA sacks Head of Legal over “The Returned Bribe” scandal

Journalism That Serves The People’s Interest

Sign up for The Fourth Estate’s newsletter and get our latest stories delivered straight to your inbox.

The Fourth Estate

The Fourth Estate is a non-profit, public interest and accountability investigative journalism project of the Media Foundation for West Africa (MFWA). Our aim is to promote independent and critical research-based journalism that holds those in power answerable to the people they govern.

Latest Stories

GHS201,000 SOCO irrigation projects fail to provide water for Bolgatanga farmers
Terrible NLA-KGL Deal: Government indulges in merry-go-round over release of interministerial committee report
$33 million loans, grants spent on streetlights in 14 years, yet darkness prevails
Government’s attempt to revive poultry industry struggles to deliver on key promises

Quick Links

  • About The Fourth Estate
  • MFWA.org
  • Honours
  • Privacy & Terms of Use

© 2025 | The Fourth Estate – A Project of the Media Foundation of West Africa